DETAILS
We recently completed some electrical works for our client, Ei Group at The Metropolitan in Didsbury.
Site were experiencing issues with the board tripping in the trade kitchen, so we sent out our Senior Electrician to investigate. Upon investigation, it became apparent that the board required replacing as this is a very busy food led pub, and any further disturbances to site would have a huge impact on trade.
The works completed were replacing the Distribution Board with a new Hager 18th Edition board, fixed wire test and a bigger mains installed, which was upgraded from 125amp to 250amp.
Our engineers worked through the night and ensured all works complete ready for site to re-open in the morning.